Contract No:
HK/2009/05 Wanchai Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work
(Stage 1) Environmental
Permit no. EP-356/2009, Further Evironmental permit nos. fep-01/356/2009,
fep-02/356/2009 and FEP-03/356/2009 Quarterly
Environmental Monitoring
and Audit Report
- March
to MAY 2010 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED
by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
9 July 2010 |
1.1    Scope of the Report
1.2    Structure of the Report
2.   Project Background
2.1    Background
2.2    Scope of the Project and Site Description
2.3    Division of the Project Responsibility
2.4    Project Organization and Contact Personnel
2.5    Project Organization and Contact Personnel
3.   Monitoring Requirements
3.1.    Noise Monitoring
3.2.    Air Monitoring
3.3.    Water Quality Monitoring
4.   Monitoring Results
4.1.    Noise Monitoring Results
4.2.    Air Monitoring Results
4.3.    Water Monitoring Results
4.4.    Waste Monitoring Results
5.1.    Noise Monitoring
5.2.    Air Monitoring
5.3.    Water Quality Monitoring
5.4.    Site Audit
5.5.    Review of the Reasons for and the Implications of
Non-compliance
5.6.    Summary of action taken in the event of and follow-up
on non-compliance
6.   Complaints, Notification of Summons and Prosecution
7.   Cumulative Construction Impact due to the Concurrent Projects
lIST OF
TABLES
Table I      Principle Work Activities for Contract no. HY/2009/11
Table II     Site Preparation Works for Contract no.
HK/2009/01
Table III     Site Preparation Works for Contract no.
HK/2009/02
Table 2.1    Schedule 2 Designated Projects under this
Project
Table 2.2   Details of Individual Contracts under the
Project
Table 2.3   Contact Details of Key Personnel
Table 2.4    Principle Work Activities for Contract no.
HY/2009/11
Table 2.5    Site Preparation Works for Contract no.
HK/2009/01
Table 2.6    Site Preparation Works for Contract no.
HK/2009/02
Table 3.1   Noise Monitoring Station
Table 3.2   Air Monitoring Station
Table 3.3    Marine Water Quality Stations for Water
Quality Monitoring
Table 3.4   Marine Water Quality Monitoring Frequency
and Parameters
Table 4.1    Noise Monitoring Stations for Contract
no. HY/2009/11
Table 4.2   Water Monitoring Stations for Contract
no. HY/2009/11
Table 4.3   Details of Waste Disposal for Contract no.
HY/2009/11
Table 4.4   Details of Waste Disposal for Contract no.
HK/2009/01
Table 4.5   Details of Waste Disposal for Contract no.
HK/2009/02
Table 6.1   Cumulative Statistics on Complaints
Table 6.2   Cumulative Statistics on Successful
Prosecutions
lIST OF FIGUREs
Figure 2.1     Project
Layout
Figure 2.2     Project Organization Chart
Figure 3.1
     Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 2.1   Environmental
Mitigation Implementation Schedule
Appendix 3.1   Action and Limit Level
Appendix 4.1   Noise Monitoring Graphical
Presentations
Appendix 4.2   Water
Quality
Monitoring Graphical Presentations
Appendix 5.1   Event Action Plans
Appendix 5.2   Summary
for Notification of Exceedance       
Appendix 6.1   Complaint Log
Appendix 8.1   Construction Programme of Individual Contracts
Construction Activities for the
Reported Period
Table I     Principle Work Activities for Contract no. HY/2009/11
March
2010 |
April
2010 |
May
2010 |
Dredging works,
Special Hoarding erection and
Erection of Refuse Collection Point (RCP) |
Dredging Works;
Construction of haul road for Harbour Height;
Construction of break water;
Construction of special site hoarding and
Construction of Community Liaison Center (CLC). |
Sediment dredging;
Breakwater demolition;
Special site hoarding construction;
Casting Caisson Seawall (in Mainland China); and
Casting Seawall Block (in Mainland China) |
Table II    Site Preparation Works for Contract no. HK/2009/01
March
2010 |
April
2010 |
May
2010 |
No site preparation
works |
Interim Engineer’s Principal Office at Works areas WA1
Erection of interim Engineer’s Principal Office at
Works areas WA2
Trial Pile staging, silt screen and silt curtain
Hoarding erection along the southern side &
eastern side of the site
Marine site investigation for cross harbour water
mains and reclamation.
Dewatering at existing pump houses is completed.
Inspection and structural condition
Fabrication of special made flat top barge for
dredging inside the HKCEC water channel
Production of pipes and fittings for cooling water
mains
Installation of inclinometer no. E1.
Ground investigation for P1 pipe pile wall. |
Erection of interim Engineer’s Principal Office at
Works areas WA2;
Pre-drilling works and fabrication of staging for
trial pile, derrick barge is carrying out transportation of materials to the
designated pile position;
Hoarding erection along the southern and eastern side;
Marine ground investigation;
Installation of geotechnical instrumentation is
underway and inclinometers points of E1, E2, E3, E4 and E8
Fabrication of pipe pile wall staging at the existing
promenade piled deck;
Inspection and structural condition survey, field
measurement for pumping stations P1, P3, P4 and P5;
Fabrication of special made flat top barge for
dredging inside the HKCEC water channel;
Silt screens installation for HKCEC Phase 1,
Government Buildings, China Resources, Great Eagle & Harbour Centre,
Telecom House, Shui On and HKAPA;
Temporary silt curtain installation at HKCEC Extension
(Pumping Station P6);
Fabrication of silt screens for Sheung Wan &
Kowloon South Pumping Station, and remaining HKCEC Extension;
Temporary works on the existing promenade piled deck
for installation of pipe pile wall P1;
Existing RC. Parapet on the north side of water
channel near Expo Drive West Bridge was removed partially; removal of rock
amour on sloping seawall is in progress;
Fabrication of mud barges and crane barge for dredging
within HKCEC water channel; and
Wheel washing facility at the north entrance to the
water channel. |
Table III    Site Preparation Works for Contract no. HK/2009/02
March
2010 |
April
2010 |
May
2010 |
No site preparation
works |
Removal Major construction activities for existing
footing at WSD Salt Water Pumping Station;
Site clearance; and
Hoarding & fencing erection |
Installation of Silt Screen and Silt Curtain;
Construction of Temporary Seawall (Sheet Pile);
Road Modification Works;
Removal Existing Footing at WSD Salt Water Pumping
Station;
Pre-drilling Works at WSD Salt Water Pumping Station;
Site Clearance; and
Hoarding Erection |
Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam Geotechnics Limited (LGL) has
been appointed to work as the
Environmental Team (ET) for Contractor No. HK/2009/05
Wan Chai Development Phase II and Central –Wan Chai Bypass  Sampling, Field
Measurement and Testing Work (Stage 1) to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the
approved Environmental Impact Assessment (EIA) Report for Wan Chai Development
phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the
EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and
auditing work carried out in accordance to the Section
10.4 of EM&A Manual
and  /span>Environmental Monitoring and Audit
Requirements /span>
under Particular Specification Section 27.
1.1.3.
This report documents the
finding of EM&A works during the period from 17th March
2010 to 27th May 2010.
Section 1     Introduction
 details the scope and structure of the report.
Section 2     Project
Background  summarizes background and scope of the
project, site description, project organization and contact details of key personnel
during the reporting period.
Section 3     Monitoring
Requirements
 summarizes all monitoring parameters, monitoring locations, monitoring
frequency, duration and action
plan.
Section 4     Monitoring
Results  summarizes the monitoring results
obtained in the reporting period.
Section 5     Compliance
Audit  summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 6     Complaints, Notification of summons and Prosecution
 summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 7     Cumulative Construction Impact due to the
Concurrent Projects  summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section 8     Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai
Bypass and “Central-Wan Chai Bypass and Island Eastern Corridor Link 
(hereafter called “the Project  are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA)
Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register
No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and
11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to
provide relief to the very congested east-west Connaught Road Central/Harcourt
Road / Gloucester Road Corridor (the Corridor) which is currently operating
beyond its capacity. The CWB will provide relief to the existing congestion
along the Corridor and cater for the anticipated growth of traffic on Hong Kong
Island. Without the CWB and its access roads, there will not be sufficient
capacity to serve the heavy traffic demands at both strategic and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure
2.1.
2.2.2.
The study area encompasses existing developments
along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses
include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the
Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the
Royal Hong Kong Yacht Club (RHKYC), the Police Officers' Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The
scope of the Project comprises:
Land formation for key
transport infrastructure and facilities, including the Trunk Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
Extension, modification,
reprovisioning or protection of existing storm water drainage outfalls,
sewerage outfalls and watermains affected by the revised land use and land
formation works mentioned above
Upgrading of hinterland
storm water drainage system and sewerage system, which would be rendered
insufficient by the land formation works mentioned above
Provision of the ground
level roads, flyovers, footbridges, necessary transport facilities and the
associated utility services
Construction of the new
waterfront promenade, landscape works and the associated utility services
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure
2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1   Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. 
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits (FEP) such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
In the reporting period, Contract no. HY/2009/11 -
Central  Wanchai Bypass, North Point Reclamation under the Project has been
commenced on 17 March 2010. Two Contracts under the Project are anticipated to
be commenced in end of June 2010. 
The details of individual contracts are summarized in Table2.2.
Table 2.2  Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II  Central –Wanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
End of June 2010 |
DP1, DP2 |
Pending |
||
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai
East |
DP3, DP5 |
End of June 2010 |
DP1 |
Pending |
||
HY/2009/11 |
Wan Chai Development Phase II and Central - Wan Chai Bypass - North
Point Reclamation |
DP3 |
17 March 2010 |
2.4.1.
Civil Engineering and
Development Department and Highways Department are the overall project
controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass
respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2607 0838 |
2687 2322 |
Engineer for CWB |
Chief Resident Engineer |
Mr. David Kwan |
3916 1800 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Ho Wing Tai |
9306 1356 |
|||
Construction Manager |
David Wong |
9653 8635 |
|||
Construction Manager |
Wilson Lau |
5183 1270 |
|||
Construction Manager |
Alex Tsang |
9194 9383 |
|||
Environmental Officer
(Compliance Manager) |
Ho Wing Tai |
9306 1356 |
|||
Environmental Engineer |
Ken Yang |
9262 6791 |
|||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Anthony Wu |
3658 3004 |
|||
Environmental Officer (Compliance Manager) |
Mr. Barry Leung |
3658 3031 |
|||
Environmental Engineer |
Ms. Flora Ng |
3658-3064 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
During this reporting period, the principle work
activities for Contract no. HY/2009/11 are summarized in Table2.4.
Table 2.4   Principle Work Activities for Contract no.
HY/2009/11
March 2010 |
April 2010 |
May 2010 |
Dredging works,
Special Hoarding erection and
Erection of Refuse Collection Point (RCP) |
Dredging Works;
Construction of haul road for Harbour Height;
Construction of break water;
Construction of special site hoarding and
Construction of Community Liaison Center (CLC). |
Sediment dredging;
Breakwater demolition;
Special site hoarding construction;
Casting Caisson Seawall (in Mainland China); and
Casting Seawall Block (in Mainland China) |
2.5.2.
Major marine activities
for Contract no. HK/2009/01 are anticipated to be commenced in the end of June
2010. The major site preparation works in this reporting periods are summarized
in Table 2.5.
Table 2.5   Site Preparation Works for Contract no.
HK/2009/01
March 2010 |
April 2010 |
May 2010 |
No site preparation
works |
Interim Engineer’s Principal Office at Works areas WA1
Erection of interim Engineer’s Principal Office at
Works areas WA2
Trial Pile staging, silt screen and silt curtain
Hoarding erection along the southern side &
eastern side of the site
Marine site investigation for cross harbour water
mains and reclamation.
Dewatering at existing pump houses is completed.
Inspection and structural condition
Fabrication of special made flat top barge for
dredging inside the HKCEC water channel
Production of pipes and fittings for cooling water
mains
Installation of inclinometer no. E1.
Ground investigation for P1 pipe pile wall. |
Erection of interim Engineer’s Principal Office at WA2;
Pre-drilling works and fabrication of staging for
trial pile, derrick barge is carrying out transportation of materials to the
designated pile position;
Hoarding erection along the southern and eastern side;
Marine ground investigation;
Installation of geotechnical instrumentation is
underway and inclinometers points of E1, E2, E3, E4 and E8
Fabrication of pipe pile wall staging at the existing
promenade piled deck;
Inspection and structural condition survey, field
measurement for pumping stations P1, P3, P4 and P5;
Fabrication of special made flat top barge for
dredging inside the HKCEC water channel;
Silt screens installation for HKCEC Phase 1,
Government Buildings, China Resources, Great Eagle & Harbour Centre,
Telecom House, Shui On and HKAPA;
Temporary silt curtain installation at HKCEC Extension
(Pumping Station P6);
Fabrication of silt screens for Sheung Wan &
Kowloon South Pumping Station, and remaining HKCEC Extension;
Temporary works on the existing promenade piled deck
for installation of pipe pile wall P1;
Existing RC. Parapet on the north side of water
channel near Expo Drive West Bridge was removed partially; removal of rock
amour on sloping seawall is in progress;
Fabrication of mud barges and crane barge for dredging
within HKCEC water channel; and
Wheel washing facility at the north entrance to the
water channel. |
2.5.3.
Major construction activities
for Contract no. HK/2009/02 are anticipated to be commenced in the end of June
2010. The major site preparation works in this reporting periods are summarized
in Table 2.6.
Table 2.6   Site Preparation Works for Contract no.
HK/2009/02
March 2010 |
April 2010 |
May 2010 |
No site preparation
works |
Removal Major construction activities for existing
footing at WSD Salt Water Pumping Station;
Site clearance; and
Hoarding & fencing erection |
Installation of Silt Screen and Silt Curtain;
Construction of Temporary Seawall (Sheet Pile);
Road Modification Works;
Removal Existing Footing at WSD Salt Water Pumping
Station;
Pre-drilling Works at WSD Salt Water Pumping Station;
Site Clearance; and
Hoarding Erection |
2.5.4.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix
2.1.
Noise Monitoring Stations
3.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 3.1
and Figure
3.1.  /span>Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.1  Noise
Monitoring Station
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4a |
Causeway
Bay Community Centre |
M5b |
City
Garden |
M6 |
HK Baptist Church Henrietta
Secondary School |
M7a |
Harbour
Building |
Noise Monitoring Parameters, Frequency
and Duration
3.1.2.
The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700
and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for
data auditing, statistical results such as L10 and L90 shall also be obtained
for reference.
3.1.3.
Noise monitoring shall be carried
out at all the designated monitoring stations. The monitoring frequency shall
depend on the scale of the construction activities. The following is an initial
guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
one set of measurements between 0700 and 1900
hours on normal weekdays.
3.1.4.
If
construction works are extended to include works during the hours of 1900  
0700 as well as public holidays and Sundays, additional weekly impact monitoring
shall be carried out during respective restricted hours periods. Applicable
permits under NCO shall be obtained by the Contractor.
Air Quality Monitoring Stations
3.2.1.
The air monitoring stations for the Project
are listed and shown in Table 3.2 and Figure
3.1. Appendix 3.1
shows the established Action/Limit Levels for the monitoring works.
Table 3.2  Air
Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
Causeway Bay Community Centre |
Causeway
Bay |
CMA3a |
Future CWB site office at Wanchai
Waterfront Promenade |
Causeway
Bay |
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to
Pedestrian Plaza |
Wan Chai |
CMA6a |
Future AECOM site office at Work
Area |
Wan Chai |
MA1b |
Harbour
Building |
Central |
Air Monitoring Parameters, Frequency and
Duration
3.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
3.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
3.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
3.3.1.
The EIA Report has identified that the key
water quality impact would be associated with the dredging works during the
construction phase. Marine water
quality monitoring for dissolved oxygen (DO), suspended solid (SS) and
turbidity is therefore recommended to be carried out at selected WSD flushing
water intakes. The impact monitoring
should be carried out during the proposed dredging works to ensure the
compliance with the water quality standards.
Water Quality Monitoring Stations
3.3.2.
It is proposed to monitor the water quality
at 9 WSD salt water intakes and 12 cooling water intakes along the seafront of
the Victoria Harbour. The proposed water quality monitoring stations of the
Project are shown in Table 3.3 and Figure
3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.3   Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt
Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling
Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4 |
Wan Chai Tower and Great Eagle
Centre |
835932.8 |
815888.2 |
C5 |
Sun Hung Kai Centre |
836250.1 |
815932.2 |
C6 |
World Trade Centre |
837009.6 |
815999.3 |
C7 |
Windsor House |
837193.7 |
816150.0 |
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed
HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung
Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
Windsor House (Temporary Dilution) |
837245.2 |
816156.6 |
Water Quality Parameters and frequency
3.3.3.
Monitoring of dissolved oxygen (DO),
turbidity and suspended solids (SS) shall be carried out at WSD flushing water
intakes and cooling water intakes. DO and Turbidity are measured in-situ while
SS is determined in laboratory. 
3.3.4.
In association with the water quality
parameters, other relevant data shall also be measured, such as monitoring location/position,
time, sampling depth, water temperature, pH, salinity, dissolved oxygen (DO)
saturation, weather conditions, sea conditions, tidal stage, and any special
phenomena and work underway at the construction site etc.
3.3.5.
The interval between two sets of monitoring
should not be less than 36 hours except where there are exceedances of Action
and/or Limit Levels, in which case the monitoring frequency will be
increased. Table 3.4 shows the
proposed monitoring frequency and water quality parameters. Duplicate in-situ measurements and water
sampling should be carried out in each sampling event. For selection of tides for in-situ
measurement and water sampling, tidal range of individual flood and ebb tides
should be not less than 0.5m.
Table
3.4  Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week baseline
monitoring period |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine
construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
After
completion of marine construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1. For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than 0.5m.
2. Turbidity
should be measured in situ whereas SS should be determined by laboratory.
4.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designed project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure 2.1 and Figure 3.1.
The monitoring results are presented in according to the Individual Contract(s).
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
4.1.1.
The proposed division of noise monitoring
stations for Contract no. HY/2009/11 are summarized in Table 4.1 below:
Table 4.1
  Noise Monitoring Stations for Contract no.  /span>HY/2009/11
Station |
Description |
M4a |
Causeway Bay Community Centre |
M5b |
City Garden |
4.1.2.
Day time and evening period noise monitoring
was conducted at the City Garden and Causeway Bay Community Centre once per
week in the reporting period.
4.1.3.
Three action level exceedances
were recorded due to the noise complaints, on 8 April and 4 May 2010. There
were complained on the construction noise nuisance from the dredging work
activities during restricted hours. Contractor’s site practical and measurement
results were reviewed. There were found no non-compliance and considered as invalid
exceedances. The details of the complaints can be referred to Section 6 and Appendix 6.1.
4.1.4.
Two limit level
exceedances were recorded at M4a on 8 April and 4 May 2010. All exceedances were investigated and
found not to be attributed to the project works as major
noise source was obtained from the Island Eastern Corridor. It can be
concluded that the exceedances were not due to the project.
4.1.5.
Noise monitoring results measured in this
reporting period are reviewed and summarized. 
Details of graphical presentation can be referred in Appendix
4.1. 
Contract
no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at
HKCEC and Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  
Wan Chai Bypass at WanChai East
4.1.6.
The commencement of marine
construction works for Contract nos. HK/2009/01 and HK/2009/02 are anticipated
in the end of June 2010. The noise monitoring will be commenced concurrently
with the commencement of construction works for these two contracts.
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
4.2.1.
The major construction activities of Contract
no. HY/2009/11 was dredging works in the reporting period. No major dust impact
is anticipated to be caused by the dredging works. Air monitoring will be
commenced from the filling work for Contract no. HY/2009/11.Therefore, no air
monitoring was conducted in the reporting period.
Contract
no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at
HKCEC and Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  
Wan Chai Bypass at WanChai East
4.2.2.
No major dust impact is anticipated to be
caused by the site preparation works. Air monitoring will be commenced from the
filling works for Contract no. HK/2009/01 and HK/2009/02. Therefore, no air
monitoring was conducted in the reporting period.
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
4.3.1.
The proposed division of water monitoring
stations for Contract no. HY/2009/11 are summarized in Table 4.2 below:
Table 4.2  Water Monitoring Stations for Contract no.  /span>HY/2009/11
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
4.3.2.
Water quality monitoring
were conducted at 6 designated monitoring stations namely WSD9, WSD10, WSD15,
WSD17, C8 and C9 on 57 tidal monitoring events during the reporting period.
4.3.3.
Due to the amber rainstorm
warning and thunderstorm on 19 May 2010 during mid-ebb, we concern about the safety
during work over water under adverse weather and consider the water quality
being substantially affected by urban runoff did not represent the normal
impact condition. At such, water
quality monitoring for this tide was cancelled.
4.3.4.
For the suspended solid,
total fifteen action level exceedances and eleven limit level exceedances were recorded in the reporting
period. The details of exceedances are as follows:
Mid-flood
Two limit level
exceedances were recorded at WSD17;
Four action level and two
limit level exceedances were recorded at C8; and
Five action level and five
limit level exceedances were recorded at C9
Mid-ebb
One action and one limit
level exceedances were recorded at WSD17;
Two action level
exceedances were recorded at C8; and
Three action level and one
limit level exceedances were recorded at C9
4.3.5.
For the turbidity, total three action level
and ten limit level exceedances were recorded in the reporting period. The details of exceedances are as follows:
Mid-flood
Four limit level
exceedances were recorded at C8; and
Two action level and five
limit level exceedances were recorded at C9
Mid-ebb
One action level and one
limit level exceedances were recorded at C8; and
4.3.6.
Investigation found that the numerous exceedances
were mainly due to the numerous unknown outfalls from the nearby coastal area
enclosed by the silt screen. It causes
the potential for accumulation and trapping of pollutants behind the silt
screens and may lead to potential water quality deterioration at the seawater
intake points.
4.3.7.
Water monitoring results measured in this
reporting period are reviewed and summarized. 
Details of graphical presentation can be referred in Appendix
4.2.
Contract
no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at
HKCEC and Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  
Wan Chai Bypass at WanChai East
4.3.8.
Water monitoring for Contract no.
HK/2009/01 and HK/2009/02 is anticipated to be commenced on end of June. Installations
of silt screen and silt curtain are untaken in the reporting period.
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
4.4.1.
Non-inert
C&D waste and marine sediment were disposed of in the reporting period. Details
of the waste flow table are summarized in Table 4.3
Table 4.3  Details
of Waste Disposal for Contract no. HY/2009/11
Waste
Type |
Quantity this quarter, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
4.72 |
4.72 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Marine Sediment (Type 1  Open Sea Disposal) |
36,000 |
36,000 |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
46,000 |
46,000 |
East of Sha Chau |
There were
marine sediments Type 1  Open Sea Disposal and Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal marine sediment
disposed in the reporting period. The maximum dredging rate in North Point
Shoreline Zone is 3,000m3 per day in the reporting period, which is complied
with the criteria listed in Table 5.10 of EIA Report Register No. AEIAR-125/2008.
Contract no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai
Bypass at HKCEC
4.4.2.
Non-inert
C&D waste was disposed of for the site preparation works in this reporting
period. Details of the waste flow table are summarized in Table 4.4.
Table 4.4  Details
of Waste Disposal for Contract no. HK/2009/01
Waste
Type |
Quantity this quarter, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
24 |
24 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Marine Sediment (Type 1  Open Sea Disposal) |
NIL |
NIL |
N/A |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
NIL |
NIL |
N/A |
Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan
Chai Bypass at WanChai East
4.4.3.
Non-inert C&D waste was disposed of for
the site preparation works in this reporting period. Details of the waste flow
table are summarized in Table 4.5.
Table 4.5  Details
of Waste Disposal for Contract no. HK/2009/02
Waste
Type |
Quantity this quarter, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
22 |
22 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Marine Sediment (Type 1  Open Sea Disposal) |
NIL |
NIL |
N/A |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
NIL |
NIL |
N/A |
5.0.1.
The Event Action Plan for construction noise,
air quality and water quality are presented in Appendix 5.1.
5.1.1.
Three action level exceedances
were recorded due to the noise complaints, on 21 March and 4 May 2010. There
were complained on the construction noise nuisance from the dredging work
activities during restricted hours. Contractor’s site practical and measurement
results were reviewed. There were found no non-compliance and considered as
invalid exceedances. The details of the complaints can be referred to Section 6
and Appendix 6.1.
5.1.2.
Two limit level
exceedances were recorded at M4a on 8 April and 4 May 2010. All exceedances
were investigated and found not to be attributed to the project works as major noise source was obtained from the Island
Eastern Corridor. It can be concluded that the exceedances were not
due to the project.
5.2.1.
No air monitoring was conducted in this
reporting period.
5.3.1.
For the suspended solid, the details of exceedances
in the reporting period are as follows:
Mid-flood
Two limit level
exceedances were recorded at WSD17;
Four action level and two
limit level exceedances were recorded at C8; and
Five action level and five
limit level exceedances were recorded at C9
Mid-ebb
One action and one limit
level exceedances were recorded at WSD17;
Two action level
exceedances were recorded at C8; and
Three action level and one
limit level exceedances were recorded at C9
5.3.2.
For the turbidity, the details of exceedances
in the reporting period are as follows:
Mid-flood
Four limit level
exceedances were recorded at C8; and
Two action level and five
limit level exceedances were recorded at C9
Mid-ebb
One action level and one
limit level exceedances were recorded at C8; and
5.3.3.
Frequent action
and limit level exceedances of turbidity and suspended solid were recorded at
C8 and C9. Major exceedances were occurred during the mid-flood tide in the
water quality monitoring. Investigation was found that the numerous unknown outfalls
from the nearby coastal area enclosed by the silt screen at C8 and C9. It causes the potential for accumulation and
trapping of pollutants behind the silt screens and may lead
to potential water quality deterioration at the seawater intake points. Contractor
was reminded to avoid the pollutant and refuse entrapment problems.
Besides, regular
maintenance of the silt screens and refuse collection shall be performed at the
monitoring stations at regular intervals on a daily basis.
5.3.4.
The exceedances were recorded at WSD17. No muddy boom was observed during the water
monitoring. Reviewed the data of the nearest monitoring station to the marine
work area in the same tide, no exceedance was recorded. As such, it is
concluded as natural variation and non-project related exceedance. Summary for
notification of exceedances can be referred to Appendix 5.2.
5.4.1.
There was no non-compliance from the site
audits in the reporting period. During environmental site inspections conducted
during the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all
deficiencies after receipt of notification.
5.5.1.
No project-related non-compliance from
monitoring was recorded in the reporting period.
5.6.1.
There was no particular action taken since no project-related
non-compliance was recorded from the site audits and environmental monitoring
in the reporting period.
6.0.1.
Three noise complaints were recorded
regarding the construction noise emission from the dredging works at North
Point district. Investigations for the complaints
were found no non-compliances with respect to the EM&A requirements. The
complaint on 21 March 2010 was also related to dark smoke emission from
dredger. Routine inspection was
strengthened on checking dark smoke emission from diesel operating plant and
equipment. The details of cumulative
complaint log and summary of complaints are presented in Appendix 6.1.
6.0.2.
No notification
of summons or prosecution was received in the reporting period. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
6.1 and Table 6.2 respectively.
Table 6.1  Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
March-May 2010 |
3 |
Project-to-Date |
3 |
Table 6.2  Cumulative Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
6.0.3.
An
incident regarding the suspected breach of Marine Dumping Permit for Contract
no. HY/2009/11 by EPD letter dated 20 April 2010, RSS has conducted a site
investigation with Contractor on 22 April 2010. Contractor for Contract no.
HY/2009/11 has reported the details of the incident and their improvement
measures to EPD on 23 April 2010. According to the EPD letter dated 20 May
2010, they have invited Contractor to assist the investigation for their
explanation or clarification on the above incident. Any updated information will
be reported in the next reporting report.
7.0.1.
According to Condition 3.4 of the EP-356/2009, this
section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation,
Central-Wan Chai Baypass and Island Eastern Corridor Link projects.
7.0.2.
According to the construction programme of Central-Wan Chai Baypass and
Island Eastern Corridor Link projects, the major construction activity under
Wan Chai Development Phase II was the dredging work at North Point Reclamation
Stage 1 in the reporting period. The major environmental impact was water
quality impact at North Point.  /span>No
construction activities were undertaken in the Central-Wan Chai Baypass and
Island Eastern Corridor Link projects.
7.0.3.
The major environmental impacts generated from the Central Reclamation
Projects were located along the coastline of Central and Admiralty while only dredging
work at North Point Reclamation Stage 1 was in operation in this reporting
period. Besides, water quality
mitigation measures were properly in place for the dredging works under
Contract no. HY/2009/11 in this reporting period. No project–related
exceedance were recorded. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Wan Chai Development
Phase II and Central Reclamation was insignificant.
8.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2.
Two noise monitoring at M4a - Causeway Bay
Community Centre was recorded marginally exceeded the limit level in the
reporting period. After review the contractor’s site practices and site investigation,
it was found that the major noise source was contributed from the traffic noise
of the Island Eastern Corridor during the measurement and was not due to the
Project.
8.0.3.
There were three complaints regarding noise
nuisance from the dredging works in North Point District. The complaint on 21
March 2010 was also related to dark smoke emission from dredger. Routine inspection was strengthened on
checking dark smoke emission from diesel operating plant and equipment. Investigations
for the complaints were found no non-compliances with respect to the EM&A
requirements.
8.0.4.
Numerous action and limit exceedances of SS
concentration and turbidity were found in the reporting period. Investigation
was found that discharges from outfalls located near seawater intake monitoring
stations are major influencing factors that adversely impact water quality. It
can be concluded that the exceedances were influenced by either adverse factors
or ambient conditions and were unrelated to the marine works for the Project.
8.0.5.
The construction programmes of individual contracts
are provided in Appendix 8.1.